Heritage Run Townhomes

<< Back to List of Projects

Development: 99 unit townhouse community
Location: Osceola County
Developer: Flagship Development

Heritage Run TownhomesBurkett Engineering, Inc. provided civil engineering services to Flagship Development throughout the development of the Heritage Run Townhomes community.  Our services began with rezoning the property to PCF (planned commercial development) and working through the Osceola County CDP process.  We then prepared engineering improvement plans (EIP) per County criteria.  Finally, we provided construction administration services during the project’s construction in 2008.

Heritage Run TownhomesThe project features 99 townhouse units in 17 buildings as well as a pool and cabana.  Stormwater treatment is provided in one wet detention pond.  Utilities design services included water, reuse, and sewer tie-ins to the Toho Water Authority system.  An on-site lift station provides the tie-in to the TWA system.

Off-site work included a right turn lane addition on Boggy Creek Road.